The Project Got More Expensive and the Cushion Is Gone

Alfonso Martínez Ruiz
Founder and Chief Executive Officer, Montclare Capital Partners · Published August 2026 · Reviewed August 2026

The structure is up, the works are advanced, and the numbers no longer close. Prices moved after tender, the programme slipped, a few problems in the ground took their share, and the contingency that was meant to absorb all of it has been spent. What remains of the facility, plus what remains of the equity, no longer reaches the end of the building. Every developer who builds long enough eventually stands in this exact spot.

It is an uncomfortable position, but it is not usually a fatal one. Projects fail at this point not because the money ran short, but because of what the developer does in the weeks after discovering it. There is a sequence that preserves the project and the developer’s control of it, and there is a set of instinctive reactions that reliably destroy both. The difference between them is worth being precise about.

First, establish the real cost to complete

Nothing useful can happen until there is one credible number: the true cost of finishing the building from today. Not the budget as it was, not the shortfall as it feels, but a verified cost to complete, built up from the current state of the works, the contractor’s account as it actually stands, the claims and variations still unresolved, the professional fees remaining, and the financing costs of the real programme, including the delay. It should be prepared or at least reviewed independently, because a number produced under pressure by the person who needs it to be small will convince nobody, starting with the lender.

The habitual error is the serial revision. The developer announces a shortfall, then a slightly larger one a month later, then another. Each individual number seemed defensible when given; together they tell every counterparty that the developer does not control his own project, and they poison the negotiations that follow. One honest number, with a margin for the remaining unknowns, is worth more than three optimistic ones. Whatever new money enters this project, from whatever source, will be sized against a verified cost to complete. Producing that number is not preparation for the solution. It is the first half of the solution.

The number also has to be complete in an unglamorous way. Delay is itself a cost: interest runs through every additional month, insurance and site costs continue, and a contractor kept on site longer has claims of his own. A cost to complete that covers the bricks but not the time will be wrong in a few months, and it will be wrong in the direction that destroys credibility. The test to apply is simple: if this number is right, no one ever needs to be asked for money on this project again.

The lender already knows, or shortly will

In a structured development financing, drawdowns are released against certified progress, which means a monitoring surveyor is comparing spend and progress against plan at every certificate. A developer who believes the funding gap is his private information is usually mistaken about how private it is, and the certification cycle sets a clock on the conversation. That leaves a choice that will shape everything afterwards: arrive at the lender with the verified number and a plan, or be discovered by a failed cost to complete test and arrive as a problem.

The difference in reception is not sentimental. A lender facing a funding gap has a range of responses, from constructive to defensive, and its choice depends largely on its assessment of the person across the table. A developer who presents the deviation early, explains its causes, brings an independent number and proposes how the gap will be filled is giving the lender reasons to work with him. A developer who stretched the truth through two certificates before the surveyor forced the issue has spent the one asset this negotiation runs on, which is credibility.

It helps to understand the lender’s own arithmetic. A half-built project is a bad asset for a bank: enforcement means owning a stopped construction site, retendering the works and explaining the position internally. Almost any credible route to a finished building is better for the lender than that, which is why lenders faced with an honest plan more often engage with it than not. The facility will not quietly grow, and the bank will not fund the gap by default. But the lender’s interest and the developer’s interest still point at the same outcome, a completed building, and a developer who frames the conversation around that shared outcome is negotiating with the current, not against it.

Preparation for that conversation matters as much as its timing. The lender will want to understand why the budget failed, because the cause shapes its confidence in the cure: an overrun driven by market-wide input prices reads very differently from one driven by scope changes the developer kept approving. It will want to see that the contractor is stable and still committed, that the permit position is clean, and that the sales assumptions behind the end value still hold. Arriving with those answers assembled, rather than promising to find them, is the difference between a meeting that opens a negotiation and a meeting that opens a file review.

The options that actually exist

The first option is the developer’s own: new equity, from the sponsor or the existing shareholders. It is usually the fastest and the cheapest in every way that is not cash, because it brings no new counterparty, no new documentation and no new control rights. Where the capacity exists, even partially, it also transforms every other conversation, since a sponsor visibly putting more of his own money behind the project is the strongest possible signal to everyone else being asked for theirs.

The second is restructuring the existing financing. The facility was built for a budget and a programme that no longer exist, and it can be rebuilt for the ones that do: the remaining tranches resized against the verified cost to complete, the term extended to match the real programme, the milestones and release conditions reset so the project can actually pass its own tests. Lenders entertain this when the updated numbers still show a project worth finishing, and the price is usually paid in margin, fees, additional security or tighter controls rather than in the developer’s ownership.

The third is new capital from outside: a partner or a junior layer entering mid-project. This money exists and it solves real gaps, but it should be approached with clear eyes. It will require the verified cost to complete, its own review of the works, and a price that reflects entering a project that has already missed its budget, paid in return, in control, or in both. Alongside it sits a fourth, partial option where the market allows: bringing revenue forward through unit pre-sales or a forward commitment on part of the scheme, which reduces the gap and demonstrates demand at the same time. What every one of these routes has in common is the entry ticket. All of them begin with the number from the first section, which is why that number comes first.

What not to do

The instinctive reactions are worth naming, because each one converts a funding problem into a worse one. The first is silence: stretching the contractor’s payments, slowing certificates, quietly hoping sales or prices rescue the gap. Delay compounds the shortfall through interest and claims, and concealment spends credibility with the one counterparty whose cooperation will be needed. The gap does not stay still while it is being hidden. It grows.

The second is mutilating the product. Cutting specification and scope to close the gap feels like discipline, but savings that reduce the end value, breach the permit or compromise what buyers were promised are not savings. They shrink the very number, the completed value, against which every rescue option is sized, and a scheme value-engineered into a worse building can lose more on the exit than it saved on the works. Related to it is the war with the contractor: escalating every claim into a dispute mid-build. There may be genuine claims, and they should be preserved, but a contractor pushed into conflict or insolvency while the building is open converts a shortfall into a stopped site, and a stopped site is the most expensive outcome available.

The third is desperate money: short-term finance at a price, taken quickly, with no defined exit, to keep the works moving another few months. Expensive capital with a plan can be rational. Expensive capital instead of a plan merely moves the crisis a season later and adds a new creditor to it, usually with security and default terms that make the eventual restructuring harder. The test for any new money in this situation is the same test a bridge loan must pass: not what it costs, but what repays it, and what happens if that event is late.

The asset only exists finished

Every option in this situation should be judged against a single fact: a half-built project is worth less than the money already inside it, and a finished one is the only version that pays anyone back. The lender, the sponsor, the contractor and any new capital are all, whether they feel it or not, on the same side of that line. The developer’s task is to organise them around it, with a verified number, an early conversation and a plan that reaches completion, and to accept that the price of the rescue is paid by the equity, because that is where overruns have always lived.

Handled that way, the position is recoverable more often than it looks from inside. Projects finish late and over budget every year and still repay their debt and return something to their owners, because someone kept the works moving and the counterparties aligned. The structure of the original financing matters enormously here. In one Dutch development, the financing was set up from the outset in a land tranche and a construction tranche, with drawdowns tied to certified progress of the works, precisely so that deviations surfaced while there was still capital to correct them, and the project kept the means to finish. The developers who survive this moment best are usually the ones whose structure was built by people who assumed it would come.

That is also the lesson to carry to the next project. The cushion that is gone was the difference between this situation being an accounting event and being a crisis, and the next budget’s contingency will be sized by someone who now knows exactly what it is for. The discipline that rescues a project mid-build, one number, early disclosure, a structure that pays for completion, is the same discipline that, applied a year earlier, would have made the rescue unnecessary.

Montclare does not act as a lender. It structures transactions, prepares the file and coordinates financing with authorised institutions.